Update construction progress of The River Thu Thiem in March 2022
– Continuing the work of finishing the landscape.
– Completing finished painting, aluminum and glass of the façade.
– Continuing the work of finishing stone tiling of plant boxes and finishing the facilities.
– Continuing MEPF works of from upper floors to basements.